SGE
16.4 MW hydroelectric facility, developed by Boralex, located on the Matagami River, Ontario.
- Gemitech: Provide studies and detailed engineering of the plant, the 13.8 / 44kV station and the 44 / 120kV interconnect station and the 44kV line connecting the two substations
- Lignec: Completion of the power plant, substations and line construction
- Transmag Energy: Supply of 20MVA transformers from each of the substations